Uploaded image for project: 'Red Hat Process Automation Manager'
  1. Red Hat Process Automation Manager
  2. RHPAM-630

Can't compile process with reusable subprocess when new marshaller is enabled

    XMLWordPrintable

Details

    • ER1
    • Hide
      https://github.com/kiegroup/kie-wb-common/pull/1741
      please reopen if PR did not fix this
      Show
      https://github.com/kiegroup/kie-wb-common/pull/1741 please reopen if PR did not fix this
    • Hide
      • Enable new marshaller implementation (-Dbpmn.marshaller.experimental=true)
      • Create simple process with one script task called "subprocess"
      • Create new process which runs "subprocess" as reusable subprocess
      • Build project
      Show
      Enable new marshaller implementation (-Dbpmn.marshaller.experimental=true) Create simple process with one script task called "subprocess" Create new process which runs "subprocess" as reusable subprocess Build project

    Description

      It is not possible to build project with reusable subprocess when new marshaller is enabled (see figures in attachment). Compilation fails with following exception:

      Process 'process' [test.process]: Node 'Subprocess' [1] SubProcess you can only set independent to 'false' only when 'Wait for completion' is set to true.

      However, diagram properties show that "Independent" is false and "Wait for Completition" is set to true.

      Attachments

        Activity

          People

            evacchi Edoardo Vacchi (Inactive)
            jpetrlik@redhat.com Jiri Petrlik
            Jiri Petrlik Jiri Petrlik
            Jiri Petrlik Jiri Petrlik
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: