      Description of problem:

      It is not possible to complete Human Task when

      • two or more embedded sub processes are modelled within one main process
      • Human Task is located within this embedded sub process
      • Java Security Manager is enabled

      Version-Release number of selected component (if applicable):
      BPM Suite 6.0.2
      BPM Suite 6.0.3

      How reproducible:
      always

      Steps to Reproduce:
      1. Import attached BPMN process into business-central (change task actor accordingly)
      2. Start the process, claim the task, complete the task
      3. Observe the exception

      Actual results:

      It is not possible to complete the task

      Expected results:
      It is possible to complete the task

      Attachments

        Activity

          People

            rzhang+1@redhat.com Cheng Zhang (Inactive)
            rhn-support-agiertli Anton Giertli
            Jan Hrcek Jan Hrcek (Inactive)
            Jan Hrcek Jan Hrcek (Inactive)
            Kris Verlaenen, Marek Baluch, Rajesh Rajasekaran
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: