    Description

      1. add a stage to the diagram
      2. add another stage to the stage
      3. add a subprocess to the second stage
      4. set multiple process variables to the subprocess and stage
      5. save the diagram and load the diagram

      Issue: the data type of the first subprocess's process variable is missing