Uploaded image for project: 'WildFly'
  1. WildFly
  2. WFLY-5850

Can't deploy an EJB to a WildFly 10 server migrated from EAP 6.4

    XMLWordPrintable

Details

    • Bug
    • Resolution: Done
    • Critical
    • 10.1.0.CR1, 10.1.0.Final
    • None
    • EJB
    • None

    Description

      I just tried to migrate a standalone.xml server from clean EAP 6.4.0 to WildFly 10.0.0.CR4 and then deploy the server-side part of the ejb-remote quickstart:

      git clone git@github.com:jboss-developer/jboss-eap-quickstarts.git
      cd jboss-eap-quickstarts/
      git checkout -b 6.4.x origin/6.4.x
      cd ejb-remote/server-side/
      mvn clean package -s ../../settings.xml
      cd target
      unzip .../jboss-eap-6.4.0.zip
      unzip .../wildfly-10.0.0.CR4.zip
      cp jboss-eap-6.4/standalone/configuration/standalone.xml wildfly-10.0.0.CR4/standalone/configuration/test.xml
      ./wildfly-10.0.0.CR4/bin/standalone.sh -c test.xml --admin-only
      
      # on a separate console
      ./wildfly-10.0.0.CR4/bin/jboss-cli.sh -c --controller=localhost:9999
      /subsystem=threads:remove
      /extension=org.jboss.as.threads:remove
      /subsystem=web:migrate
      shutdown
      
      # on the original console
      cp jboss-ejb-remote-server-side.jar wildfly-10.0.0.CR4/standalone/deployments/
      ./wildfly-10.0.0.CR4/bin/standalone.sh -c test.xml
      

      What I get is this horrible stack trace:

      15:35:50,913 ERROR [org.jboss.msc.service.fail] (MSC service thread 1-2) MSC000001: Failed to start service jboss.deployment.unit."jboss-ejb-remote-server-side.jar".POST_MODULE: org.jboss.msc.service.StartException in service jboss.deployment.unit."jboss-ejb-remote-server-side.jar".POST_MODULE: WFLYSRV0153: Failed to process phase POST_MODULE of deployment "jboss-ejb-remote-server-side.jar"
      	at org.jboss.as.server.deployment.DeploymentUnitPhaseService.start(DeploymentUnitPhaseService.java:154) [wildfly-server-2.0.0.CR8.jar:2.0.0.CR8]
      	at org.jboss.msc.service.ServiceControllerImpl$StartTask.startService(ServiceControllerImpl.java:1948) [jboss-msc-1.2.6.Final.jar:1.2.6.Final]
      	at org.jboss.msc.service.ServiceControllerImpl$StartTask.run(ServiceControllerImpl.java:1881) [jboss-msc-1.2.6.Final.jar:1.2.6.Final]
      	at java.util.concurrent.ThreadPoolExecutor.runWorker(ThreadPoolExecutor.java:1142) [rt.jar:1.8.0_66]
      	at java.util.concurrent.ThreadPoolExecutor$Worker.run(ThreadPoolExecutor.java:617) [rt.jar:1.8.0_66]
      	at java.lang.Thread.run(Thread.java:745) [rt.jar:1.8.0_66]
      Caused by: javax.validation.ValidationException: Unable to create a Configuration, because no Bean Validation provider could be found. Add a provider like Hibernate Validator (RI) to your classpath.
      	at javax.validation.Validation$GenericBootstrapImpl.configure(Validation.java:271)
      	at org.hibernate.validator.internal.cdi.ValidationExtension.<init>(ValidationExtension.java:109)
      	at sun.reflect.NativeConstructorAccessorImpl.newInstance0(Native Method) [rt.jar:1.8.0_66]
      	at sun.reflect.NativeConstructorAccessorImpl.newInstance(NativeConstructorAccessorImpl.java:62) [rt.jar:1.8.0_66]
      	at sun.reflect.DelegatingConstructorAccessorImpl.newInstance(DelegatingConstructorAccessorImpl.java:45) [rt.jar:1.8.0_66]
      	at java.lang.reflect.Constructor.newInstance(Constructor.java:422) [rt.jar:1.8.0_66]
      	at java.lang.Class.newInstance(Class.java:442) [rt.jar:1.8.0_66]
      	at org.jboss.as.weld.deployment.WeldPortableExtensions.tryRegisterExtension(WeldPortableExtensions.java:53)
      	at org.jboss.as.weld.deployment.processors.WeldPortableExtensionProcessor.loadAttachments(WeldPortableExtensionProcessor.java:121)
      	at org.jboss.as.weld.deployment.processors.WeldPortableExtensionProcessor.deploy(WeldPortableExtensionProcessor.java:81)
      	at org.jboss.as.server.deployment.DeploymentUnitPhaseService.start(DeploymentUnitPhaseService.java:147) [wildfly-server-2.0.0.CR8.jar:2.0.0.CR8]
      	... 5 more
      
      15:35:50,921 ERROR [org.jboss.as.controller.management-operation] (Controller Boot Thread) WFLYCTL0013: Operation ("deploy") failed - address: ([("deployment" => "jboss-ejb-remote-server-side.jar")]) - failure description: {"WFLYCTL0080: Failed services" => {"jboss.deployment.unit.\"jboss-ejb-remote-server-side.jar\".POST_MODULE" => "org.jboss.msc.service.StartException in service jboss.deployment.unit.\"jboss-ejb-remote-server-side.jar\".POST_MODULE: WFLYSRV0153: Failed to process phase POST_MODULE of deployment \"jboss-ejb-remote-server-side.jar\"
          Caused by: javax.validation.ValidationException: Unable to create a Configuration, because no Bean Validation provider could be found. Add a provider like Hibernate Validator (RI) to your classpath."}}
      

      When I deploy the same JAR to a clean install of WildFly 10.0.0.CR4, it works just fine. This suggests that something (probably the EJB subsystem?) doesn't correctly parse/serialize the legacy configuration. Or something like that.

      Attachments

        Issue Links

          Activity

            People

              sdouglas1@redhat.com Stuart Douglas
              lthon@redhat.com Ladislav Thon
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: