Uploaded image for project: 'JBoss Transaction Manager'
  1. JBoss Transaction Manager
  2. JBTM-3064

After a crash active LRA's are left in a limbo state

    XMLWordPrintable

Details

    • Bug
    • Resolution: Done
    • Major
    • 5.9.1.Final
    • 5.9.0.Final
    • LRA
    • None
    • Low

    Description

      If an LRA coordinator crashes with active LRA's (ie ones that have not yet been asked to finish) then when the coordinator is restarted they do not appear in the coordinators list so they cannot be ended.

      The fix is to ensure that the LRA periodic recovery module adds them back into the coordinators list of active LRA's.

      Attachments

        Issue Links

          Activity

            People

              rhn-engineering-mmusgrov Michael Musgrove
              rhn-engineering-mmusgrov Michael Musgrove
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: